Lesson 7: Critical paths and the minimum completion time

A project with two critical paths

SkillsCritical pathsFloat times

Worked example

  • Complex familiar
  • Technology free

For the school formal project, find the EST, LST and float of each activity, the critical path/s and the minimum completion time.

1 of 4 steps
  1. Step 1: Forward scan

    AA, BB: EST 0. CC, EE (after AA): EST 3. DD (after BB): EST 2. FF (after DD): 2+4=62 + 4 = 6. GG (after CC): 3+6=93 + 6 = 9. HH (after EE, FF, GG): max⁡(3+2,6+6,9+3)=12\max(3 + 2, 6 + 6, 9 + 3) = 12. Finish: 12+2=1412 + 2 = 14.

    14 weeks14 \text{ weeks}

Try a similar one

A fresh question of the same kind, checked as you answer, with hints and a full solution.

Method

  1. Scan forward for ESTs and backward for LSTs.

  2. Critical activities have float 0.

  3. Join them into every start-to-finish path; check each totals the minimum completion time.

Watch out for

  • Stopping after finding one critical path. BB and DD also have zero float, which signals a second one.