Lesson 8: Solving scheduling problems
What do the delays do to the garden?
SkillsScheduling problemsFloat times
Worked example
The community garden is planned to open in 20 days, with critical path ––––.
(a) The site survey () starts 3 days late. Will the garden still open on time?
(b) Separately, the volunteers clearing the weeds () are delayed by 7 days. When will the garden open?
(c) Both delays happen. When will the garden open?
Step 1: Find the floats
From the scans: has EST 0, LST 4, float 4. has EST 3, LST 9, float 6.
Step 2: Delay to A
The delay (3 days) is less than 's float (4 days), so the project is not delayed. Check: –––– becomes and ––– becomes .
Step 3: Delay to D
The delay (7 days) is 1 day more than 's float (6 days), so the project is 1 day late. Check: ––– becomes .
Step 4: Both delays
is on both paths through and , so recheck every path: –––– ; –––– ; ––– .
Floats are shared along a path. Once uses 3 days of slack, has only days left, so a 7-day delay costs 4 days.
Answer
(a) Yes — the 3-day delay is within 's 4 days of float, so it still opens on day 20. (b) The garden opens 1 day late, after 21 days. (c) The garden opens after 24 days, 4 days late, and ––– becomes the critical path.
Try a similar one
A fresh question of the same kind, checked as you answer, with hints and a full solution.
Method
Compare each delay with the activity's float.
For combined delays, recalculate the length of every path; the longest gives the new completion time.
Watch out for
Adding the effects separately in (c): day late. Delays on the same path use up the same float.