Lesson 8: Solving scheduling problems

What do the delays do to the garden?

SkillsScheduling problemsFloat times

Worked example

  • Complex unfamiliar
  • Technology free

The community garden is planned to open in 20 days, with critical path BB–EE–FF–HH–II.

(a) The site survey (AA) starts 3 days late. Will the garden still open on time?

(b) Separately, the volunteers clearing the weeds (DD) are delayed by 7 days. When will the garden open?

(c) Both delays happen. When will the garden open?

1 of 4 steps
  1. Step 1: Find the floats

    From the scans: AA has EST 0, LST 4, float 4. DD has EST 3, LST 9, float 6.

Try a similar one

A fresh question of the same kind, checked as you answer, with hints and a full solution.

Method

  1. Compare each delay with the activity's float.

  2. For combined delays, recalculate the length of every path; the longest gives the new completion time.

Watch out for

  • Adding the effects separately in (c): 0+1=10 + 1 = 1 day late. Delays on the same path use up the same float.