Lesson 5: Forward scanning and earliest starting times

Forward scan of the kitchen renovation

SkillEarliest starting times

Worked example

  • Simple familiar
  • Technology free

Use a forward scan to find the EST of every activity in the kitchen renovation and its minimum completion time.

1 of 5 steps
  1. Step 1: Event 1

    The start: earliest time 0. So AA and BB have EST 0.

Try a similar one

A fresh question of the same kind, checked as you answer, with hints and a full solution.

Method

  1. Start event at 0.

  2. At each event: largest of (earliest time at tail + duration) over the arrows in.

  3. The earliest time at an event is the EST of the activities leaving it.

  4. The finish event's earliest time is the minimum completion time.

Watch out for

  • Taking the smallest value at event 4 (4), which would start FF before EE is finished.