Lesson 4: Precedence tables and project networks

Drawing the garden shed network

SkillProject networks

Worked example

  • Simple familiar
  • Technology free

Draw an activity-on-arc network for the garden shed project.

ActivityDuration (days)Immediate predecessors
A2—
B3—
C2A
D4B, C
E2D
F3D
G2F
H1E, G
1 of 6 steps
  1. Step 1: Start event

    Draw event 1. AA and BB have no predecessors, so both leave event 1.

Try a similar one

A fresh question of the same kind, checked as you answer, with hints and a full solution.

Method

  1. Activities with no predecessors leave the start event.

  2. Each activity leaves the event where all its immediate predecessors end.

  3. Activities with no successors end at the finish event.

  4. Number events so arrows point to larger numbers; check every activity against the table.

Watch out for

  • Drawing DD from the end of CC only, forgetting it must also wait for BB.

  • Giving EE and HH separate finish events: there is only one finish.

Save your progress with a free account