Lesson 8: Modelling with straight-line graphs

Building a model from a table of costs

SkillsBuilding and using linear modelsEquations from graphs and pointsInterpreting gradient and intercept

Worked example

  • Complex familiar
  • Technology active

A hardware store lists the cost of hiring a box trailer.

Hire time, hh (hours)2345
Cost, CC ($)47597183

(a) Show that the relationship is linear, and find its equation.

(b) Interpret the gradient and the CC-intercept.

(c) Predict the cost of hiring the trailer for 8 hours.

1 of 5 steps
  1. Step 1: Check the differences

    Each extra hour adds 59−47=71−59=83−71=$1259 - 47 = 71 - 59 = 83 - 71 = \$12. Equal steps in hh give equal changes in CC, so the relationship is linear.

Try a similar one

A fresh question of the same kind, checked as you answer, with hints and a full solution.

Method

  1. Check for constant differences to confirm the data is linear.

  2. Gradient from two points; intercept by substituting one point.

  3. Interpret both in context, then use the model to predict.

Watch out for

  • Reading the intercept as 47 (the cost for 2 hours, not 0 hours).

  • Predicting by doubling the 4-hour cost: 2×71=1422 \times 71 = 142 counts the fixed charge twice.