A cane harvesting contractor harvested 9600 tonnes of cane in 800 hours of work in 2024. In 2025, after buying a faster harvester, it harvested 10 500 tonnes in 750 hours. Calculate the percentage change in labour productivity (tonnes per hour), to one decimal place, and explain which factor of production caused it.

1 of 4 steps
  1. Step 1: Productivity in 2024

    9600÷800=129600 \div 800 = 12 tonnes per hour.

    12 t/h12\ \text{t/h}

Try a similar one

A fresh question of the same kind, checked as you answer, with hints and a full solution.

Method

  1. Productivity = output ÷ hours, for each period.

  2. Percentage change = (new − original) ÷ original × 100.

  3. Name the source of the change: capital, skills, technology or organisation.

Watch out for

  • Finding the percentage change in total output (9.4%) instead of output per hour.